2017 Flood review event

Status
Past review

We made a final decision on 23 May 2018  to approve Aurizon Network’s $16.90 million (pre-escalation) tropical cyclone Debbie review event application, as amended on 21 March 2018.

On 28 March 2017, tropical cyclone Debbie caused widespread damage to Aurizon Network’s infrastructure in Central Queensland. Where a review event occurs, Aurizon Network may propose to vary reference tariffs under clause 5 of schedule F of the 2016 access undertaking.

Aurizon Network proposed to recover costs arising from cyclone Debbie in tariffs to apply on an interim basis between 1 January 2018 and 30 June 2018. These interim tariffs were also reflected in a draft amending access undertaking (DAAU) to extend the termination date of the 2016 undertaking to 30 June 2018, which was approved by us on 9 November 2017. When a replacement undertaking (UT5) is approved there will be a final reconciliation and true-up so that only approved costs are recovered.

Aurizon Network’s review event submission can be downloaded below.

Date Action
22 September 2017 Aurizon Network submitted $16.93 million claim
18 October 2017 Aurizon Network provided RSM Australia cost review
7 November 2017 Aurizon Network provided supplementary information letter
10 November 2017 Submissions closed
21 March 2018 Aurizon Network amended its claim to $16.90 million
20 April 2018 The QCA published an expert report and draft decision
3 May 2018 Submissions closed
23 May 2018 QCA made final decision to approve the claim

Reports and papers

Title Document
23 May 2018 Final report QCA – Final decision on Aurizon Networks 2017 flood claim pdf, 1.58 Mb
Title Document
19 April 2018 Draft report QCA – Letter to Aurizon Network on its 2017 flood claim pdf, 215.89 Kb
19 April 2018 Draft report QCA – Draft decision on Aurizon Networks 2017 flood claim pdf, 1.06 Mb
23 March 2018 Consultant report AECOM – Review of Aurizon Networks 2017 flood claim pdf, 3.86 Mb
21 March 2018 Submission Aurizon Network – Amendment to the 2017 flood claim pdf, 893.73 Kb
Title Document
10 November 2017 Submission Anglo American – Aurizon Networks 2017 flood claim pdf, 126.52 Kb
10 November 2017 Submission QRC – Aurizon Network 2017 flood claim pdf, 74.51 Kb
Title Document
07 November 2017 Submission Aurizon Network – Supplementary Information – 2017 Flood Claim pdf, 176.46 Kb
18 October 2017 Submission Aurizon Network-RSM Australia cost review of 2017 Flood Claim pdf, 676.86 Kb
22 September 2017 Submission Aurizon Network-Submission Letter pdf, 945.19 Kb
22 September 2017 Submission Aurizon Network-2017 Flood Review Event Submission pdf, 2.75 Mb
Title Document
13 October 2017 Notice QCA – Stakeholder Notice 2017 Flood Review Event pdf, 473.12 Kb

2016 Flood review event

Aurizon Network’s Goonyella system suffered flood damage in February 2016.

On 31 October 2016, Aurizon Network sought our approval to recover $1.98 million (pre-escalation) of incremental maintenance costs resulting from the flood event, through a variation to the 2017–18 Goonyella reference tariffs.

After receiving no submissions from stakeholders, on 24 May 2017, we made a decision to approve Aurizon Network’s application.

Our letter to Aurizon Network and decision, and our consultant’s (B&H) report are available below.

Reports and papers

Title Document
24 May 2017 Final report QCA – Letter to Aurizon Network – 2016 flood review event pdf, 285.18 Kb
24 May 2017 Final report QCA decision – Aurizon Network 2016 flood review event pdf, 821.09 Kb
24 May 2017 Consultant report BH Review of the 2016 Flood Event Claim pdf, 955.10 Kb
Title Document
14 November 2016 Submission Aurizon Network – 2016 Flood Review Event pdf, 1.21 Mb

2015 Flood review event

The Moura system withstood flood damage as a result of Cyclone Marcia in February 2015.

Aurizon Network sought a variation to its reference tariffs to recover the incremental maintenance costs of $4.05 million (pre-escalation), resulting from the 2015 flood event.

On 8 December 2016, we made a final decision to approve Aurizon Network’s application. We made this decision under the transitional provisions of the 2016 access undertaking (UT4).

Our final decision, our consultant’s (Jacobs) supplementary report, and stakeholders’ comments on our October 2016 draft decision are available below.

Reports and papers

Title Document
09 December 2016 Final report QCA Final decision – Aurizon Network’s 2015 Flood Review Event pdf, 558.76 Kb
09 December 2016 Final report QCA – Letter to Aurizon Network – final decision on 2015 Flood Review Event pdf, 365.65 Kb
09 December 2016 Consultant report Jacobs – Supplementary report – 2015 Flood Review Event pdf, 984.55 Kb
Title Document
09 December 2016 Submission Aurizon Network – Response submission 2015 Flood Review Event pdf, 1.15 Mb
09 December 2016 Submission Anglo American – Response submission 2015 Flood Review Event pdf, 171.83 Kb
Title Document
13 October 2016 Draft report QCA – Draft Decision Aurizon Network 2015 Flood Review Event pdf, 739.45 Kb
13 October 2016 Draft report QCA – Letter to Aurizon Network 2015 flood Review event claim pdf, 247.14 Kb
13 October 2016 Consultant report Jacobs – Draft Report Aurizon Network’s 2015 Flood Damage Claim Review pdf, 7.34 Mb
Title Document
12 January 2016 Submission Cockatoo Submission pdf, 3.48 Mb
12 January 2016 Submission Anglo American Submission pdf, 137.64 Kb
02 December 2015 Submission AN 2015 Flood Review Event Cover Letter (redacted) pdf, 779.77 Kb
02 December 2015 Submission AN 2015 Flood Review Event Submission pdf, 2.04 Mb

(function(w,d,s,l,i){w[l]=w[l]||[];w[l].push({'gtm.start': new Date().getTime(),event:'gtm.js'});var f=d.getElementsByTagName(s)[0], j=d.createElement(s),dl=l!='dataLayer'?'&l='+l:'';j.async=true;j.src= 'https://www.googletagmanager.com/gtm.js?id='+i+dl;f.parentNode.insertBefore(j,f); })(window,document,'script','dataLayer','GTM-5H7MCMG');