In effect
Under Aurizon Network’s UT5 we may approve the prudent and efficient value of private incremental costs (PIC) associated with private infrastructure, on request from an access seeker or Aurizon Network.
The documents relating to our PIC approvals are available for download below.
On 21 December 2023, Pembroke Resources requested that we approve a PIC amount for infrastructure it had constructed for transport coal from the Olive Downs Complex to Aurizon Network’s Goonyella system.
We published a draft decision for stakeholder feedback on 26 April 2024. We received no submissions in response.
On 23 May 2024, we approved a PIC amount for the Olive Downs Complex.
All relevant documents are available for download below.
|
Title | Document | |
---|---|---|---|
23 May 2024 | Final report | Pembroke Resources PIC claim – final decision | pdf, 198.57 Kb |
18 April 2024 | Draft report | Pembroke Resources PIC claim – draft decision | pdf, 152.12 Kb |
06 March 2024 | Consultant report | Arcadis draft report (redacted) | pdf, 3.07 Mb |
21 December 2023 | Other documents | Pembroke Resources PIC claim – application | pdf, 405.78 Kb |
On 13 April 2022, Bravus Mining and Resources requested that we approve a PIC amount for its Carmichael rail loop project and connecting infrastructure.
We released a draft decision on 10 October 2022, and after consideration of all issues raised, we approved a PIC amount on 15 December 2022.
Our final decision and all relevant documents are available for download below.
|
Title | Document | |
---|---|---|---|
15 December 2022 | Final report | Carmichael private incremental cost claim – Final Decision | pdf, 166.80 Kb |
19 December 2022 | Final report | Arcadis Final Report – Carmichael private incremental cost claim | pdf, 10.18 Mb |
07 October 2022 | Draft report | Carmichael private incremental cost claim – Draft decision notice 7 Oct | pdf, 154.66 Kb |
10 October 2022 | Draft report | Arcadis Draft Report – Carmichael private incremental cost claim | pdf, 10.60 Mb |
On 9 July 2021, Sojitz MDS Mining Pty Ltd requested us to approve a PIC amount for its MDS rail and train loading project.
On 17 February 2022, we approved a PIC amount for the project.